Commissioning checklist

Use this checklist after physical installation is complete to verify the system is fully operational.

Pre-power

  • All breakers securely mounted on DIN rail

  • All power wiring terminals tightened to recommended torque: 2 Nm for breakers rated up to 25A, 3.5 Nm for breakers rated 25-80A

  • Power wiring (phase, neutral, earth) correctly terminated

  • RS485 daisy chain complete - controller through all breakers using supplied wire (rated 110°C / 600V)

  • RS485 polarity (A/B) consistent at every point

  • Edge Controller mounted, network cable ready

  • PSU connected to protected 230V AC supply

  • UPS connected if fitted (3.7V / 20Ah Li-Polymer)

  • Enclosure rated for calculated heat load

Power on

  • PSU outputting 24V DC

  • Controller LED: purple during setup

  • Controller LED: blue (OFF/idle) or red (ON/active) once connected

  • No immediate breaker trips when circuits are energised

Connectivity

  • Controller appears in Hybird OS with recent "last seen"

  • Connection type (Ethernet/Wi-Fi/LTE) as intended

Breaker discovery

  • Breaker scan shows all installed breakers

  • All Modbus IDs unique

  • No missing devices

Data verification

  • Each breaker shows: voltage, current, power, leakage, temperature, state

  • Three-phase breakers show per-phase data

  • Voltage in expected range (\~230V single-phase)

  • Leakage at normal levels (below 5 mA typical)

Labelling

  • Every breaker labelled with descriptive circuit name in Hybird OS

Remote switching test

  • Test off/on via Hybird OS on one non-critical breaker

  • State change reflected within seconds

Customer handoff

  • Dashboard URL and credentials provided

  • Support contact shared: [email protected] / +45 3020 4900

  • Eloverblik consent process initiated or scheduled